WestminsterHeader 

 

Upcoming Night Work Scheduled

Night work is scheduled to take place on Westminster Blvd. near the OCSD Seal Beach Pump Station between Seal Beach Blvd. and Kitts Hwy. 

 

Map of Seal Beach Pump Station to Kitts Away Approximate Work Area

  • Starting as early as September 14, 2020 through the end of November 2020*
  • Nighttime work hours are 9 p.m. to 6 a.m., Monday (PM) – Saturday (AM)

This night work activity is in addition to the daytime construction currently taking place. 

Construction Status

Construction is currently taking place in the City of Seal Beach between Seal Beach Blvd. and Bolsa Chica Rd. 

  • Ongoing since April 2020 through the end of December 2020*
  • Daytime work hours are 6:30 a.m. to 4 p.m., Monday – Friday
  • Starting as early as 7 a.m., temporary closures of the #1 lane on Westminster Blvd. may occur in either direction

Progress on the project continues, with approximately 3/4 miles of pipeline constructed. A project progress map for the month of September 2020 is available for viewing.

*Work dates and times are subject to change due to operational factors or inclement weather.

Be Safe on the Road

There is a lot of construction activity taking place.  Please be safe when traveling along Westminster Blvd.  Keep your eyes on the road and reduce your speeds.  The posted speed limit is 40 mph through the construction zone. 

Keep Up With Updates

Sign up for text alerts

Project Description:

The project will replace and reconstruct nearly three miles of two parallel 36-inch diameter sewer pipelines on Westminster Boulevard between Seal Beach Boulevard and Rancho Road/Hammon Place in the cities of Seal Beach and Westminster.

This project is within the Western Regional service area.