Westminster Blvd. Sewer Construction Update – October 30, 2020

Home >> News >> Westminster Blvd. Sewer Construction Update – October 30, 2020

Westminster Blvd. Sewer Construction Update – October 30, 2020

WestminsterHeader 

Construction Update

Seal Beach Pump Station (Seal Beach Blvd./Westminster Blvd.) to Kitts Hwy

Construction continues in this area with excavation and installing pipelines.

  • Ongoing – end of November 2020
  • Monday – Friday, nighttime work hours 9 p.m. – 6 a.m

Kitts Hwy to Bolsa Chica Rd.

Construction continues in this long 2-mile stretch with excavation, installing pipelines, and paving throughout the area. Some photos of the job site are below.

  • Ongoing – end of December 2020
  • Monday – Friday, 6:30 a.m. – 4 p.m.

IMG_0090

Upcoming Construction

Work in the City of Westminster is anticipated to begin as early as mid-December, starting with restriping of travel lanes on Westminster Blvd. More information will be provided as the work approaches.

***On a different project in the City of Seal Beach***

Seal Beach Blvd. between I-405 and Westminster Blvd.

As part of the future Seal Beach Pump Station project, utility investigations will be taking place.

Stay in the Know

Sign up for text alerts

Be Safe on the Road

There is a lot of construction activity taking place.  Please be safe when traveling along Westminster Blvd.  Keep your eyes on the road and reduce your speeds.  The posted speed limit is 40 mph through the construction zone. 

Project Description:

The project will replace and reconstruct nearly three miles of two parallel 36-inch diameter sewer pipelines on Westminster Boulevard between Seal Beach Boulevard and Rancho Road/Hammon Place in the cities of Seal Beach and Westminster.

This project is within the Western Regional service area.

Sign Up For Email Notifications