The project will replace and construct nearly three miles of two regional pressurized sewer pipelines (force mains) on Westminster Boulevard between Seal Beach Boulevard and Rancho Road/Hammon Place in the cities of Seal Beach and Westminster. Construction began Spring 2020 and is anticipated to be completed late 2022.
Intersection of Westminster Blvd. and Bolsa Chica Rd.
Progress through the intersection continues. Upcoming activities include backfill and paving, testing, and other miscellaneous activities to complete construction of the new pipeline through the intersection.
- Ongoing – July 2022*
- Daytime work hours: Mon – Fri, 9 a.m. – 3 p.m., occasional Sat work, 5 a.m. – 3 p.m.
- There is work scheduled for Saturday, June 25.
- Anticipate lane closures and turn restrictions.
- Nighttime work hours: Mon – Fri, 8 p.m. – 6 a.m.
- There is work scheduled for June 28 – July 1 for steel plate removal and paving.
- The 4-way traffic signal will be on *flashing red*; anticipate lane closures and turn restrictions with the various traffic control set ups as they work through the intersection in stages.
Photo above taken June 16 showing the intersection of Westminster Blvd. and Bolsa Chica Rd.
Between Bolsa Chica Rd. and Rancho Rd.
The segment of pipeline in this location was replaced using the sliplining method where a 36-inch diameter pipeline was installed into the existing 42-inch diameter pipeline. Several access pits were excavated and high density poly ethylene (HDPE) pipeline segments were fused together and pulled into the old pipeline through these access pits. Over 3,000 feet of pipeline was sliplined. Backfilling, removal of shoring, testing, and other activities continue.
- Work hours: M – F, 7 a.m. – 5 p.m.
- Lane closure hours: M – F, 8:30 a.m. – 3:30 p.m.
Near the Intersection of Westminster Blvd. and Seal Beach Blvd. (City of Seal Beach)
Work has be ongoing by OC San’s Seal Beach Pump Station facility.
- Nighttime work hours: Mon – Fri, 9 p.m. – 6 a.m.
- There is night work scheduled for June 27.
*All dates and times are subject to change due to operational factors or inclement weather.
What to Expect:
- Periodic traffic delays as a result of lane reductions and turn restrictions
- Increased noise level
- Lane closures
- Certain bus stops along the route may be affected, please watch for posted signs and visit www.OCTA.net for details.
UPCOMING WORK:
Intersection of Westminster Blvd. and Rancho Rd.
Rehabilitation of siphons, the pipes that go under the Barber City Channel and runs parallel to Rancho Road. More information will be provided as scheduled work dates are confirmed.