The project replaces and constructs nearly three miles of two regional pressurized sewer pipelines (force mains) on Westminster Boulevard between Seal Beach Boulevard and Rancho Road/Hammon Place in the cities of Seal Beach and Westminster. Construction began Spring 2020 and all underground sewer construction work was completed late 2022. Landscape and street restoration will be complete by early 2023.  Â
Construction of the two new sewer pipelines is complete. Restoration activities will continue to take place throughout the project area.
UPCOMING WORK
City of Seal Beach
LOCATION: Westminster Blvd. between Bolsa Chica Rd. and Seal Beach Blvd. Both westbound and eastbound bike lanes.Â
What:Â Â Final striping of bike lanes
When:Â Starting July 5, lasting approximately 2-3 nights
Hours:Â 9 p.m. – 5 a.m.
We understand that traffic and construction impacts can be an inconvenience and we apologize in advance and thank you for your patience. For your safety and that of our crew, please follow all traffic control measures in place and use caution while traveling through the construction zone.
*All dates and times are subject to change due to operational factors or inclement weather. Â
STAY IN THE KNOW
View the project progress map for current and future work.Â
Sign up for text alerts
Sign up for e-notifications (Subscribe to “Westminster Blvd.” in the News section)
Questions? Construction Hotline 714.378.2965 or ConstructionHotline@ocsan.gov.