The project replaces and constructs nearly three miles of two regional pressurized sewer pipelines (force mains) on Westminster Boulevard between Seal Beach Boulevard and Rancho Road/Hammon Place in the cities of Seal Beach and Westminster. Construction began Spring 2020 and all underground sewer construction work was completed late 2022. Landscape and street restoration will be complete by early 2023.  Â
Construction of the two new sewer pipelines is complete. Restoration activities will continue to take place throughout the project area. Paving occurred in the City of Seal Beach but rain did impact the work starting in the City of Westminster. See the updated paving schedule below.
Updated 3/16/23
Upcoming Work:
Westminster Blvd., University Street to Rancho Road/Hammon Place
- What:Â Â Street paving
- When:Â March 16 & 17*Â Â Due to recent rain events, pavement is too wet to start paving March 16 and will now be starting on March 17.
*Schedule subject to change due to operational factors or inclement weather.
- Work Hours:Â 7 a.m. – 6 p.m., extended hours may be needed to complete the work.
- Paving activities must be done when temperatures are at least 50°F and is therefore scheduled for daytime work.  Â
- What to Expect:
- Lane closures and turn restrictions.
- Delays when traveling through the area. Allow plenty of time to get to your destination.
- If possible, avoid the area and use alternate routes.
- Increased noise levels.
Entire Project Area – Westminster Blvd. between Seal Beach Blvd. and Rancho Road/Hammon Place
Following street paving, final striping is tentatively scheduled to occur the week of March 26. This work is anticipated to be performed at night. More information will be provided as dates and times are confirmed.
We understand that traffic and construction impacts can be an inconvenience and we apologize in advance and thank you for your patience. We are working closely with the cities of Seal Beach and Westminster and have notified them of the schedule.
*All dates and times are subject to change due to operational factors or inclement weather. Â
STAY IN THE KNOW
View the project progress map for current and future work.Â
Sign up for text alerts
Sign up for e-notifications (Subscribe to “Westminster Blvd.” in the News section)