Westminster Sewer Construction Update – June 10, 2021

Home >> News >> Westminster Sewer Construction Update – June 10, 2021

Between Seal Beach Blvd and Bolsa Chica (City of Seal Beach) 

 Lane striping is scheduled over 2 weeks during the nighttime hours between 9 p.m. – 6 a.m. on:  Monday, June 21, Tuesday, June 22 (if needed), and Monday, June 28.

Street restoration and final paving activities of over 1 mile (7,000 feet) along Westminster Blvd. between Kitts Highway (east of Seal Beach Blvd.) and Bolsa Chica Rd is taking place.  Paving has already taken place. The paving limits were primarily within the excavation area of where the construction of two new regional sewer pipelines occurred.  Lane striping will allow for vehicular travel lanes to be moved back to the original configuration before the construction project.

Following the move of travel lanes back to the original configuration, any repairs to the original bicycle lane will occur and the temporary bicycle lane that was put in as part of this project will be removed.

Seal Beach Pump Station (Intersection of Westminster Blvd and Seal Beach Blvd)

Construction is currently taking place by the Seal Beach Pump Station site.

Between Bolsa Chica and Rancho Road (City of Westminster)

This project replaces two existing side-by-side regional sewer pipelines.  In the City of Westminster, one pipeline will be replaced at a time while the other pipeline is in service 24/7 to collect and transport wastewater for treatment and recycling. The contractor is currently working on completing construction of the first sewer pipe.  Once completed and the new pipeline is put in service, the contractor will be able to start construction on the second pipe, moving in the direction from Bolsa Chica headed towards Rancho Road. The contractor has started preliminary work of the second pipe such as potholing to verify locations of existing utilities.

  • Monday – Friday. 7:30 a.m. – 5 p.m.
  • Westminster Blvd. will be reduced to one lane in each direction.
  • Any trees and vegetation removed will be replaced after sewer work is completed and restoration takes place.
  • Some activities may occur outside work hours within the k-rail sections between the hours of 7 a.m. and 7 p.m.
  • Paving at the Milan St. intersection will occur the week of June 21.

Near or at the Intersection of Westminster Blvd. and Bolsa Chica Rd.

  • Monday – Friday, 9 a.m. – 3 p.m.
  • When working in the intersection, traffic signal at the intersection will be on flashing red.  Treat as a 4-way STOP.
  • Be alert.  There will be traffic lane closures and turn restrictions. Flaggers will be onsite to assist with directing traffic.
  • Some construction activities will be loud.
  • To avoid potential traffic delays, if possible, use alternate routes to avoid the area.

*All dates and times are subject to change due to operational factors or inclement weather.

STAY IN THE KNOW

 View the project progress map for June.

Sign up for text alerts

Questions?  Construction Hotline 714.378.2965 or ConstructionHotline@ocsan.gov

Project Description:

The project will replace and reconstruct nearly three miles of two 36-inch diameter sewer pipelines on Westminster Boulevard between Seal Beach Boulevard and Rancho Road/Hammon Place in the cities of Seal Beach and Westminster.  Construction began Spring 2020 and will be completed Fall 2022.

This project is within the Western Regional service area.